What Does a Bag Supplier Send Before Your Shipment?

Six documents should arrive after confirmation: a proforma invoice, a production schedule with seven milestones, a material confirmation, the sample with its record, the inspection report, and the shipping set. Each has a purpose and a moment, and each should be checked on arrival against the confirmation.

Proforma invoice with quantity, price, currency, Incoterm and beneficiary fields highlighted
Four fields carry most of the risk: quantity by colourway, currency, Incoterm, beneficiary.
Quick answer

After an order is confirmed, six documents should arrive: a proforma invoice, a production schedule with milestones, a material confirmation, the sample with its record, the inspection report, and the shipping set of commercial invoice, packing list and transport document. Each has a purpose and a moment. The buyer job is to check each one on arrival against the confirmation, because a document checked late is a document that cannot be corrected.

The period between confirmation and shipment is a document exchange, and most buyers treat it as a wait. That is a mistake, because every document in the sequence has a moment at which it can still be corrected at no cost and a point after which correction costs money or time. A proforma invoice checked on arrival prevents a payment argument; the same document checked at the balance stage is an argument. This piece sets out what should arrive, when, what each is for, and how to check it.

What Arrives in the First Week After Confirmation?

Three documents, and their arrival is a signal that the order has been accepted and scheduled. The proforma invoice restates the commercial terms and carries the beneficiary details. The production schedule gives the milestone dates. The material confirmation records what has been bought, or is about to be bought, and in which colour. Where one of the three does not arrive, the order has been accepted but not scheduled, which is a different state.

Six documents. Each has a moment at which it can still be corrected without cost.
DocumentWhat it is forWhen it should arriveWhat to check on arrival
Proforma invoiceRestates the commercial terms and carries the payment detailsWithin days of confirmationQuantity, price, currency, Incoterm, beneficiary
Production scheduleGives the seven milestone datesWithin the first weekThat the triggers match the confirmation
Material confirmationRecords the fabric, foam, trim and hardware boughtWithin the first weekThat it matches the specification revision
Artwork proofThe branding as it will be appliedBefore the branding operationPosition, size, colour reference
Inspection reportThe result at the agreed standardAt the inspection milestoneStandard, level, class counts, verdict
Shipping setCommercial invoice, packing list, transport documentAt releaseThat the values agree with the proforma

What Is a Proforma Invoice For?

It is the commercial restatement of the order and the document the buyer pays against. It is not a tax document and it is not the document used at the customs entry, which is why the distinction with the commercial invoice matters. Its job is to make the order confirmable and payable: quantity, unit price, total, currency, Incoterm with edition and place, payment split, validity, and the beneficiary details for the transfer.

Check it against the confirmation on the day it arrives, and check four fields in particular: the quantity by colourway, the currency, the Incoterm, and the beneficiary name against the account. Those four are where discrepancies hide, and all four cost nothing to correct in the first week and are expensive to correct at the balance. Note the validity as well, because it is the date by which the material prices behind the figure still hold.

What Is the Production Schedule For?

It converts the window into dates and gives the buyer something to track. The useful version carries the seven milestones — material inward, cutting start, branding start, assembly start, inline inspection, packing completion, and final inspection with release — each with a date. The less useful version gives a single completion date, which cannot be tracked and therefore cannot be managed.

Check the triggers, not only the dates. A schedule that dates assembly from the deposit rather than from written sample approval is measuring a different interval from the one in the confirmation, and the difference can be weeks. Where the confirmation says 35-50 days from written approval, the schedule should say the same, and the completion date should follow from it.

What Is the Material Confirmation For?

It records what is actually being bought, which is not always what the specification said. Fabric substitutions, hardware pack quantities and colour references all surface here, and this is the earliest point at which a substitution can be caught. A substitution found at material confirmation is a phone call; the same substitution found at inspection is a re-work or a claim.

Read it against the compliance file as well as against the specification. Where a material carries a declaration or a test report for the destination market, a substitution can invalidate that document, and the invalidation is discovered at the worst point if nobody reads the confirmation. One line in the order — that any substitution requires written approval with the compliance effect stated — is what gives the buyer the right to be told.

What Arrives at Sampling?

The sample itself, and three things with it: a measurement record, photographs, and a statement of what was built. The sample without the record is a physical object that has to be re-measured by the buyer, and re-measuring introduces the buyer own method errors. A sample with a measurement record taken on the same method as the drawing can be checked in minutes.

Ask for the branding state to be stated explicitly. A sample that arrives unbranded, when the order is branded, is a sample that cannot be approved for appearance, and the resulting second cycle is entirely avoidable. Where artwork was not ready, ask for a branding mock-up on a separate panel shipped with the sample, so the appearance decision can be made without a second build.

What Arrives Before Packing?

Two things: the inline inspection result and the packing specification as it will be applied. The inline result is the last point at which a systematic fault can be corrected before the goods are closed in cartons, and it should carry defect counts by class rather than a narrative. The packing specification sets the carton count and the cube, which decide the freight, and it should be checked before the cartons are sealed rather than after.

The packing check is the most frequently skipped of all of them, and it is the one that produces the most expensive surprise. A carton count that differs from the plan changes the freight quote, and a carton marking that differs from the retail requirement produces a warehouse problem at the far end. Both are visible on a packing list, and both are correctable before the goods move.

Proforma invoice
Quantity by colourway, price, currency, Incoterm, beneficiary, validity
Production schedule
Seven milestone dates, and that the triggers match the confirmation
Material confirmation
Fabric, foam, trim and hardware against the specification revision
Artwork proof
Position, size and colour reference before the branding operation
Sample record
Measurements on the stated method, photographs, branding state
Inline report
Defect counts by class, and the corrective action taken
Packing list
Carton count, marking and cube before the cartons are sealed
Commercial invoice
Values agreeing with the proforma, and the description for the customs entry

What Arrives at Release?

The shipping set: the commercial invoice, the packing list and the transport document named by the Incoterm, plus the inspection report if it has not already been supplied. The commercial invoice is the document used at the customs entry and for duty in the destination market, so its description and values matter beyond the payment. Where the values disagree with the proforma, the entry is where the discrepancy surfaces.

Check the description line specifically. A bag described loosely on a commercial invoice invites a classification question at the customs entry, and a classification question delays the goods. The description should name the article, the material and the use in terms that match the classification the buyer intends to declare, and it should agree with the packing list.

Shipping document set: commercial invoice, packing list and transport document together
Three documents, checked against each other. The customs entry is where a mismatch surfaces.

What Should the Buyer Do With a Discrepancy in a Document?

Raise it in writing the same day, quote both figures, and ask which one governs. A discrepancy between a proforma invoice and the confirmation is usually a transcription error, and it is corrected in minutes if it is raised while the document is new. Raised three weeks later, the same discrepancy becomes a negotiation, because by then somebody has planned against the wrong figure.

Where the discrepancy is in the beneficiary details, stop the payment rather than querying it. That is the one case where the correct response is to pause everything and verify by a second channel, because it is the only discrepancy in this process that can cost the whole amount rather than a part of it. Everything else can be corrected after the fact; that one cannot.

How Do You Keep the Document Trail Together?

One folder per order, named by style and order date, with the documents in arrival order and a short index at the front. The index lists each document, the date it arrived, who checked it and the outcome. Four columns, and it is what makes the folder usable by somebody other than the person who created it.

Keep the emails out of it. A thread is useful while it is live and useless afterwards, because it has to be read in order to be understood. Where a decision was made in a thread, copy the decision into the index with its date. One line per decision, and the folder becomes a record rather than an archive.

What Does a Good Document Flow Tell You About the Desk?

A great deal, and it is worth reading deliberately. A desk that sends the proforma invoice, the schedule and the material confirmation without being chased is a desk that has a process. One that sends only the proforma invoice and then answers questions about dates is a desk that is reactively organised, and the buyer should expect to do more tracking. Neither is disqualifying, but they call for different levels of buyer involvement.

The second signal is whether the documents agree with each other. A schedule whose dates do not match the proforma validity, or a packing list whose carton count does not match the packing specification, indicates that documents are being produced by different people without a cross-check. That is worth knowing early, because it predicts the kind of error that surfaces at the customs entry rather than at the desk.

What Should the Buyer Send Back?

Three things, each of which the desk needs and the buyer controls: the sample approval in writing, the payment confirmation once a transfer has been made, and answers to any open field. The first starts the bulk window, the second releases the material booking, and the third prevents a clarification from becoming a delay. All three are in the buyer hands, and all three are the usual cause of a programme that stalls for non-production reasons.

Send the payment confirmation as a document rather than as a sentence. A transfer reference, the value date and the amount let the desk match the payment to the order without a search, and a payment that cannot be matched is a payment that does not release anything. Where the transfer was made through a bank that applies charges, state the net amount expected.

What Does the Buyer Owe in This Exchange?

Three things, and the sequence works better when they are stated. Prompt answers to open fields, because a clarification held on the buyer side stalls a schedule just as effectively as a delay on the other side. Written approval of the sample within the stated period, because the bulk window is calculated from it. And payment on the date the confirmation states, because a production slot was reserved against it.

Stating those three in the confirmation makes the exchange reciprocal, and it gives the buyer something to point at when an internal delay threatens the date. A document flow that records only what the desk must send tends to be treated as a desk obligation, and the buyer side of it then goes unmanaged — which is where a surprising share of delays actually originate.

How Should Documents Be Checked?

Against the confirmation, on arrival, and by a named person. Against the confirmation, because that is the agreement. On arrival, because that is when correction is free. And by a named person, because a document that everybody assumes somebody else has checked has not been checked. A one-page check list beside the folder is enough, and it is the least expensive control in the process.

Six checks. Five cost nothing to make and all six are expensive to make late.
CheckAgainst whatWhat a mismatch meansCost of finding it late
Quantity by colourwayThe confirmationA shortfall or an over-run laterAn invoice argument
Beneficiary name and accountThe proforma invoicePossible interception, or an unmatched paymentA held release, or worse
Milestone triggersThe confirmationA different interval being measuredWeeks of schedule error
Material against specificationThe signed-off revisionAn unapproved substitutionA re-work or an invalidated report
Carton count and markingThe packing specificationA freight change or a warehouse problemMoney at the far end
Invoice values against proformaThe proforma invoiceA classification or valuation questionA held customs entry

Who Should Check Each Document on the Buyer Side?

One named person, with the same discipline as the production cadence: check on arrival, initial the index, and raise any discrepancy the same day. Where the buyer side is a team, the checker is not necessarily the owner — finance checks the proforma, quality checks the inspection report, logistics checks the packing list — but one person owns the index and makes sure each document has actually been looked at.

The failure mode is a document that arrives, sits in a shared mailbox, and is assumed to have been checked by whoever usually checks that kind of document. Naming the checker per document type takes five minutes and it closes that gap entirely. Where the buyer is a single person, the discipline is simpler but no less necessary: a checklist on the folder, initialled.

What If a Document Does Not Arrive?

Ask for it by name, on the cadence, and record that it was asked for. Most missing documents are missing because nobody owns them rather than because they cannot be produced, and a named request on a weekly rhythm resolves that. Where a document is repeatedly promised and not delivered, treat it as a signal about the programme rather than about the document.

Reading the document flow

  • Expect six documents: proforma invoice, schedule, material confirmation, sample record, inspection report, shipping set.
  • Check each on arrival, against the confirmation, by a named person.
  • Check the four fields that carry the risk: quantity by colourway, currency, Incoterm, beneficiary.
  • Read the material confirmation against the compliance file, because a substitution can invalidate a report.
  • Send back three things promptly: written approval, payment confirmation, and answers to open fields.
Folder of six documents in arrival order, each initialled by the checker
Six documents, checked on arrival by a named person. That is the whole control.

Ask for the document flow up front

Ask for the six documents and the date each is expected. You get a flow that can be checked on arrival rather than argued about at the balance.

Frequently Asked Questions

What documents should arrive after an order is confirmed?

Six: a proforma invoice, a production schedule with milestones, a material confirmation, the sample with its record, the inspection report, and the shipping set.

What is a proforma invoice for?

It restates the commercial terms and carries the payment details. It is not the document used at the customs entry, which is the commercial invoice.

What should I check on a proforma invoice?

Quantity by colourway, price, currency, Incoterm with edition and place, payment split, validity, and the beneficiary name against the account.

What should a production schedule contain?

The seven milestone dates, each with a trigger matching the confirmation, rather than a single completion date.

Why does the material confirmation matter?

It is the earliest point at which a substitution can be caught. The same substitution found at inspection becomes a re-work or a claim.

What should arrive with the sample?

A measurement record taken on the stated method, photographs, and an explicit statement of the branding state.

What arrives before packing?

The inline inspection result with defect counts by class, and the packing specification as it will be applied.

What is in the shipping set?

The commercial invoice, the packing list and the transport document named by the Incoterm, plus the inspection report if not already supplied.

Why check the commercial invoice description?

A loose description invites a classification question at the customs entry, and a classification question delays the goods.

What should the buyer send back?

Three things: written sample approval, the payment confirmation with reference and value date, and answers to open fields.

How should documents be checked?

Against the confirmation, on arrival, by a named person. Correction is free at arrival and expensive later.

What if a document never arrives?

Ask for it by name on the weekly cadence and record the request. Repeated non-delivery is a signal about the programme.

People Also Ask

What does a bag supplier send after order confirmation?

A proforma invoice, a production schedule, a material confirmation, the sample record, the inspection report and the shipping set.

What is a proforma invoice used for?

To restate the commercial terms and carry the payment details, not for the customs entry.

Why check the material confirmation?

It is the earliest point to catch a substitution, which can otherwise invalidate a compliance report.

What is in the shipping document set?

The commercial invoice, the packing list and the transport document named by the Incoterm.

When should documents be checked?

On arrival, against the confirmation, by a named person, because correction is free then and costly later.